TRESSLER DRIVE WATER QUALITY IMPROVEMENT PROJECT - IRL COUNCIL COST-SHARE AGREEMENT CHANGE ORDER (RC):

 

RESOLUTION No. 27-2022; A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF STUART, FLORIDA, AUTHORIZING THE MAYOR TO EXECUTE A CHANGE ORDER TO THE COST-SHARE AGREEMENT FOR THE TRESSLER DRIVE WATER QUALITY IMPROVEMENT PROJECT WITH THE INDIAN RIVER LAGOON (IRL) COUNCIL; PROVIDING AN EFFECTIVE DATE, AND FOR OTHER PURPOSES.

 


Summary Explanation/Background Information on Agenda Request:

The City Commission previously adopted Resolution No. 66-2021 on July 12, 2021, authorizing the Mayor to execute a Cost-Share Agreement for the Tressler Drive Water Quality Improvement Project with the Indian River Lagoon (IRL) Council. Per the agreement, the IRL Council will pay the City approximately 50% of the total cost for satisfactory completion of the project, which amounts to $80,000.

 

The City Commission also previously approved Resolution No. 73-2021 on October 11, 2021, authorizing the Utilities & Engineering Department to submit a grant application for the IRL Council License Plate Funding Program through the South Florida Water Management District (SFWMD) to provide additional funding for the project. The Utilities & Engineering Department was notified by SFWMD of the award for an additional $89,980 in funding on January 11, 2022.

 

The City held off on advertising the bid for construction of the project until SFWMD awarded the additional funding. Therefore, the City made a request to the IRL Council to extend the deliverable due dates for Tasks 1, 2, & 3 of the executed IRL Council Cost-Share Agreement. In addition, the deliverable due dates are being modified to be consistent with the deliverable schedule of the new IRL License Plate Program grant.  The deliverable due dates are modified as follows:

 

Task 1    Bidding – from February 1, 2022 to May 1, 2022

Task 2    As-builts – from June 1, 2022 to September 30, 2022

Task 3   Photo of project signage, copy of website literature and social media posts – from July 31, 2022 to September 30, 2022

 

Please note this is a no cost change order.



Funding Source:

Project is included in the Fiscal Year 2021/2022 budget - Stormwater Enterprise Fund, Capital Outlay.



Recommended Action:

Move approval of Resolution No. 27-2022.

 

ATTACHMENTS:
DescriptionUpload DateType
Resolution No. 27-2022 Tressler Drive Water Quality Improvement Project Change Order2/10/2022Resolution add to Y drive
Change Order Tressler Drive2/10/2022Attachment
Resolution No. 66-20212/10/2022Backup Material
Resolution No. 73-20212/10/2022Backup Material