Title of Item:
AWARD OF WORK ORDER# 5 FOR STYPMANN BLVD AND GUY DAVIS FORCE MAIN REPAIRS (RC):
RESOLUTION No. 108-2020; A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF STUART, FLORIDA TO APPROVE THE AWARD OF WORK ORDER NO. 2019-300-W05, STYPMANN BOULEVARD FORCE MAIN IN-SITU REPLACEMENT/GUY DAVIS FORCE MAIN REPAIRS TO THE LOWEST, MOST RESPONSIVE RESPONSIBLE BIDDER, JOHNSON-DAVIS, IN THE AMOUNT OF $404,800.00 PROVIDING AN EFFECTIVE DATE; AND FOR OTHER PURPOSES.
Summary Explanation/Background Information on Agenda Request:
The Stuart City Commission awarded Request for Qualification No. 2019-300, Underground Utility Construction Services to the top four (4) most qualified firms.
Each firm was notified of the project on July 24, 2020. A mandatory pre-bid was held on August 5, 2020, three of the four firms participated. This project was competitively bid between four firms, Felix Associates, and Johnson-Davis Inc., Centerline Utilizes, Inc., and Sunshine Land Design. Two firms Johnson-Davis and Felix and Associates of Florida, Inc. submitted bids by the bid opening date and time of 1:30 pm, August 26, 2020.
Holtz Engineering the Engineer of record and Public Works staff recommends award to Johnson-Davis of Ft. Pierce, the lowest responsive and responsible bidder, for the total unit price bid amount of $404,800.00.
Funding Source:
1630-563 Project # 20044401
Recommended Action: